Jim Wells County, TX BESS 

Project Size: 9.9MW / 19.8MWh (2-hour duration)

Role: Balance of Plant (BoP) services, including engineering, BoP procurement, installation, construction, commissioning support, integration, and interconnection support

Technology: Hithium, EPC Power, Fractal EMS

Year Built: Construction begins in 2025; Commercial Operation Date (COD) – 2026 

Located in Jim Wells County, TX, this stand-alone Front of the Meter Battery Energy Storage System (BESS) project is designed to enhance grid stability within the ERCOT market. By overseeing every element of project execution—from design to integration—TruGrid delivers a comprehensive, bankable solution that reduces complexity, mitigates risk, and accelerates commercial readiness for our partners. 

Stadium Bess TruGrid Project, EPC, O&M, Integration

Reach Out. We’re Ready.